projects

Details of major projects

Company project value for erection works: 450 million bdt

Client: toshiba plant systems & services corporation (tpsc)

Matarbari power station is a 2x600-megawatt (MW) coal-fired power plant in Matarbari, Cox's Bazar, Chittagong, Bangladesh.

Coal Power Generation Company Bangladesh (CPGCBL), a state-owned enterprise of the People's Republic of Bangladesh, is the developer of the project with major funding from JICA Japan.

Completed works in Matarbari 2x600 MW Power Plant Project

MEP & instrumentation erection works in STG, WTP, WWTP, aux boiler, GIS, intake, HCSD, HSD, AWRS, ESP, bottom ash, NaOH building, workshop building & BOP

Scope & Responsibilities

01

Health, Safety & Environment

02

Quality Assurance & Quality Control

03

Material Handling

04

Logistics

05

Planning

06

Execution

07

Pre-commissioning & Testing

08

Site Inspections, Documentation & Final Submission

cable tray, conduits preassembly & installation

cable tray, conduits preassembly & installation

77,000 meters / 1305 tons

  • 01Cable Tray / Ladder:35,000 Mtrs / 750 Tons
  • 02Cable Tray Support:395 Tons
  • 03Cable Tray Cover:22,000 Mtrs / 160 Tons
  • 04GI Conduits Installations:20,000 Mtrs

cable pulling, termination and testing

1,705 km

127 KM

MV Cable

504 KM

LV Cable

532 KM

Control Cable

456 KM

Instrument Cable

41 KM

Earthing Cable

45 KM

Fiber Optic

cable pulling, termination and testing
panel installations

panel installations

810 panels

  • WWTP LV, PLC & MCC Panels: 108 Nos

  • WTP MV, LV, PLC & MCC Panels: 482 Nos

  • FGD & ESP Electrical Panels:220 Nos

instrumentation

4,990 instruments

1140 Nos

ESP, FGD Instruments

1160 Nos

WTP & WWTP Instruments

1390 Nos

ESP & Hopper System

1300 Nos

STG Building

instrumentation

21 transformers

transformer installations

  • Service Transformers21 Nos

1740 lighting points

lighting installations

  • LED Lights with Pole540 Nos
  • BOP Lighting1200 Nos
cathodic protection

cathodic protection

6 major units

  • 1MCWP Pipinp:Unit 1 & Unit 2
  • 2Water Intake Structure:Unit 1 & Unit 2
  • 3MCW Pump & Tanks:Unit 1 & Unit 2
cable termination

cable termination

24,250 termination points / 12,125 cables

  • MV Cable Termination:250 Points

  • LV Cable:12000 Points

  • Inst & Control Cable:12000 Points

6000 mtrs

piping works

  • Fire Fighting Pipe4000 mtrs

  • Plumbing uPVC Pipe2000 mtrs

770 FA devices & 2300 sprinklers

fire alarm system

  • heat / smoke detector500 nos
  • alarm horn & modules270 nos
  • sprinkler2300 nos

Site Installation Photos

Image 1
Image 2
Image 3
Image 4
Image 5
Image 6
Image 7
Image 8
Image 9
Image 10
Image 11
Image 12
Image 13
Image 14
Image 15
Image 16
Image 17

QA/QC Testing & Inspections

Image 1
Image 2
Image 3
Image 4
Image 5

Testing Photos

Image 1

motor winding test

Image 2

ondrum cable test

Image 3

cable IR test

Image 4

Image 5

transformer winding test

Image 6

DC contact test

Image 7

Image 8

cable IR test

Image 9

panel busbar insulation test

Image 10

MV cable hipot test

Material Handling

Image 1
Image 2
Image 3
Image 4